Epworth Hospital Redevelopment Pod 4 Early Works

Summary: 

​Delta Group was contracted in 2013 for the Epworth’s Redevelopment project.  W​orks included the demolition of the existing 3 storey structure at 62, Erin Street, Richmond, including a 4 level car-park along with asbestos removal.

Project Overview

Highlights :

  • ​Delta group worked cl​osely with Kane Construction to ensure the demolition and other works were carried out with minimal disruption to the operating hospital.
  • Delta carried out demolition of 2 buildings along with a 4 level car-park and was also responsible for removal of asbestos and soft strip out.

​Scope of Works :​​

​The Pod 4 early works package consisted of demolishing the existing 62 Erin Street Building, excavation of new basement levels and retention system in preparation for the Pod 4 Main Works (Construction). ​​​​

Delta Group was contracted for removal of asbestos, demolition of a 3-storey office building and a 4 level car-park.

The bulk of the works entailed asbestos removal, soft strip out, link bridge demolition and main structure demolition which included brick walls, reinforced concrete slabs, beams, walls and columns.

Delta Group worked very closely with Kane Construction and the Epworth Hospital, to ensure the works were completed safely with minimal disruption to the operating Hospital.

Other Information