The scope of works included:
The location of the site within the high density James Street mixed use precinct demanded an effective stakeholder engagement plan in conjunction with an innovative works programme. For example, we were able to minimise noise and vibration impacts (and to address stakeholder objections and concerns) by devising a unique blasting technique to reduce the volume of rock breaking required to complete civil excavation works.
In total, we blasted more than 12,000 cubic metres of rock and excavated more than 30,000 cubic metres of spoil – without incident.