The scope of works included:
We successfully deconstructed the tank farms and associated structures using specialised plant and equipment, including excavators and precision shear attachments to peel/fold each tank before processing the scrap steel onsite. The foundations were broken down using excavators with hammer attachments and buckets, before loading waste onto articulated trucks for offsite disposal.
Once our demolition works were complete, we undertook remediation and rehabilitation of 22,000 cubic metres of contaminated soil, including: